Wednesday, March 29, 2006

 

Building Update

Work is progressing well and is on schedule.
Principal's Quarters - walls up to roof level -100%.
Toilet Block - walls, roof , plaster -100%.
3 storeyed school building- Column foundations 68% completed

Comments: Post a Comment